What the Ratings Actually Describe
FD30 and FD60 refer to fire resistance demonstrated by testing a complete door assembly — leaf, frame, seals and ironmongery together — for 30 or 60 minutes respectively. The figure is not a property of the leaf alone, which is why swapping components for non-matching items, or fitting a leaf into an unsuitable frame, undermines the basis of the rating.
| Consideration | FD30 | FD60 |
|---|---|---|
| Tested performance | 30 minutes of fire resistance under test conditions | 60 minutes of fire resistance under test conditions |
| Where it is typically seen | Frequently specified for doors within dwellings, flat entrances, HMO bedrooms and general escape routes, depending on the building's fire strategy | More often associated with higher-risk compartmentation, plant and service rooms, and certain commercial or multi-storey arrangements |
| Leaf construction | Usually a lighter core and thinner leaf than an equivalent FD60 | Typically heavier and thicker, which affects hinge, frame and closer selection |
| Seals | Intumescent seals suited to the tested detail; smoke seals where an S rating applies | Intumescent provision to the tested detail, often more substantial; smoke seals where required |
| Ironmongery | Hinges, closers and latches compatible with the tested assembly and the leaf weight | Heavier-duty hinges and closers are commonly needed for the increased leaf weight |
| Glazing | Only glazing, beads and seals matching the tested detail for that doorset | Only glazing, beads and seals matching the tested detail for that doorset, generally to a higher specification |
Where the Specification Comes From
The rating a particular door needs is a building-specific question. It follows the compartmentation strategy for that property, not the appearance or thickness of what is already hanging there. We confirm the requirement from documentation before pricing replacement doorsets.
- The building's fire strategy and compartmentation design
- The current fire risk assessment and any action list
- An existing fire door inspection report
- Original building or refurbishment records and product information
- Advice from a competent fire safety professional where the requirement is unclear
Why Guesswork Is a Poor Basis
Choosing a rating by eye creates two problems. Under-specifying leaves a door that does not match the building's strategy. Over-specifying brings a heavier leaf that the existing frame, hinges and closer may not suit, and can cause closing and latching problems that lead to the door being propped open.
Where a formal fire door inspection report is required, this can be arranged through a specialist fire door inspection contractor. Parsec Fire Doors assesses doors on site to confirm the scope and cost of remedial or replacement work, and works from the specification recorded for the building.
Practical Points When Replacing a Doorset
Whichever rating applies, the installation detail decides whether the doorset performs as intended once it is in the opening.
- Structural opening size, frame condition and how the frame is fixed
- Leaf weight and the hinges, closers and latches needed to suit it
- Threshold detail, floor finishes and the resulting undercut
- Any glazing, vision panels or air transfer requirements
- Access, occupancy and making the opening secure between visits
- The records and product information you will hold afterwards
What you should end up holding afterwards is covered in our guide to installation and handover documentation. If the existing door has faults rather than the wrong rating, our guide to common fire door defects may be the better starting point.
Need replacement doorsets priced?
Tell us the door sizes, quantities and the specification recorded for the building, and we will come back with a costed proposal.
- · Property type and site postcode
- · Approximate number of doors
- · Any inspection report or FRA action list
- · Photographs of the doors in question
Already have a fire door inspection report or FRA action list? Attach it securely to the enquiry form and we will price the remedial or replacement work door by door.
Frequently Asked Questions
Talk Through Your Door Schedule
Send the specification, door schedule or inspection report you already hold and we will price the supply and installation work required.